Ensuring Compliance with the EPA’s New Boiler Rules
January 1,
2012
In 2011, the EPA enacted the Area Source Rule, making it mandatory for
many commercial, institutional and manufacturing facilities to monitor fuel
usage on a monthly basis and conduct biennial tune-ups. Some facilities also are required to conduct
a one-time energy assessment and others must regularly meet emissions
limits.
The new rule applies to any area source facility, which includes the
majority of facilities in the United States.
An area source facility is one that emits less than 10 tons per year of
any single air toxic and 25 tons or more per year of any combination of air
toxics.
A comprehensive list of the regulated air toxics can be found on the EPA
website at www.epa.gov. Methods for
calculating a facility’s emissions are detailed in the “Preferred and
Alternative Methods for Estimating Air Emissions from Boilers” guide, available on the EPA site.
When the EPA
proposed the Area Source Rule, the agency also proposed the Major Source Rule (also
known as Boiler MACT or BMACT), designed to reduce boiler and process heater
emissions at large sources of air toxics.
The EPA is
reconsidering parts of the Major Source and Area Source Rules. While it is
carrying out the formal reconsideration process, the Area Source Rule is in
effect. However, the Major Source Rule is
delayed while the EPA is reconsidering this rule.
Factors that Determine Compliance Requirements
Compliance
requirements, many of which take effect in 2012, vary depending upon the type
of fuel burned, the size of the boiler and its age.
All area sources
can be classified as one of the following fuel subcategories:
- Biomass -- any
boiler that burns at least 15 percent biomass on an annual heat input basis.
- Coal -- any boiler
that burns any solid fossil fuel and no more than 15 percent biomass on an
annual heat input basis.
- Oil – any
boiler that burns any liquid fuel and is not in either the biomass or coal
subcategories.
- Gas-fired -- any
boiler that burns gaseous fuels, including: natural gas, process gas, landfill
gas, coal-derived gas, refinery gas, hydrogen, or biogas, not combined with any
solid fuels. To maintain status as a gas-fired boiler, periodic burning of a
liquid fuel cannot exceed a combined total of 48 hours during any calendar year.
Boiler size, as it relates to the Area Source Rule, is expressed in
terms of rated design heat input capacity and is measured in million British thermal
units per hour, or MMBTU/hr. Boilers
that are larger or equal to 10 MMBTU/hr input have different requirements than
those that are smaller.
The age of a boiler is also a factor in determining compliance
requirements. A boiler is considered an
existing source if construction or reconstruction began on or before June 4,
2010. A boiler is considered a new source if construction or reconstruction
began after June 4, 2010, and the applicability criteria was met when
construction started, or the boiler switched from firing natural gas fuel to a
solid fossil fuel, biomass, or liquid fuel after June 4, 2010.
Meeting
Compliance Requirements
Under the new Area Source Rule, facilities must meter and record their fuel
usage monthly.
There are several products available to help facilities monitor fuel
usage. Sophisticated control and monitoring
systems such as the Cleaver-Brooks Hawk work with an advanced SCADA
(Supervisory Control and Data Acquisition) computer system to control a
boiler’s room balance while gathering continuous, real-time data.
If an integrated boiler room control is not the best solution for your
facility, another option to consider is a standalone transmitter that provides
pertinent boiler information to a PC or server within a facility’s existing
network. This particular system can
monitor up to three fuels per boiler.
There are also monitoring systems available that collect fuel usage on
boiler systems that are not equipped with intelligent controls. For example, the Universal Monitoring System
gathers data for up to two fuels per boiler, utilizing a transmitter to send
the information to a PC or facility network server.
Conducting
Boiler Tune-ups
Another requirement of the EPA rules is a boiler tune-up, which must be
conducted for all biomass- and oil-fired boilers as well as for new and
existing coal-fired area source boilers with a heat input capacity of less than
10 MMBTU/hr.
For existing boilers, the first tune-up should be completed by March 21,
2012, and for new sources, the tune-up was to be done by May 20, 2011 or upon
start-up of the boiler, whichever is later.
Subsequent tune-ups are required every other year.
For the initial tune-up, the following steps are necessary:
- Inspect the burner and clean or replace any
components, as necessary.
- Adjust the burner as necessary to optimize the
flame pattern.
- Inspect air-to-fuel ratio control system to ensure
system is calibrated and functioning properly.
- Optimize emissions of carbon monoxide (CO)
consistent with manufacturer’s specifications, if available.
- Measure CO and O2 levels in exhaust
before and after tune-up.
- Record the type and amount of fuel used for
previous 12 months (the effective date of the rule was May 20, 2011, so the
first tune-up will have less than 12 months of reporting).
- Submit a signed statement indicating that a boiler
tune-up was completed.
The same steps are required for subsequent tune-ups. The compliance certificates should be kept at
the facility and submitted upon request.
Arranging
an Energy Assessment
For large, existing biomass-, oil- and coal-fired boilers, a one-time energy
assessment is required under the Area Source Rule. The assessment must be
performed by a qualified energy assessor, such as Armstrong or Swagelok Energy
Advisors. The energy assessment should
include:
- Visual inspection of the boiler system.
- An evaluation of operating characteristics of the
facility.
- An inventory of major systems consuming energy away
from affected boiler(s).
- A review of architectural and engineering plans,
facility operation and maintenance.
- A list of major energy conservation measures.
- A list of energy savings potential.
- A report detailing ways to improve efficiency.
A facility must keep the results of the energy assessment on site for
submission when requested.
Meeting
Emissions Limits
Under the Area Source Rule, large, coal-fired boilers must meet
emissions limits for CO and mercury (Hg).
Existing sources have until May 21, 2014 to comply, but new sources
(built or rebuilt after June 4, 2010) were required to meet the stated
emissions limits by May 20, 2011. New
sources also must meet the emissions limits for particulate matter (PM).
Oil- and biomass-fired boilers built prior to June 4, 2010 do not have
to meet emissions limits, but those built after that date must have met PM
emissions limits by May 20, 2011 or upon startup.
Facilities that are now required to meet stricter emissions limit
requirements have several options to help meet the requirements or avoid
applicability altogether. Among the
options are: burner conversions that can increase fuel efficiency and decrease emissions,
fuel-train conversions that can help minimize or eliminate the use of oil, or a
boiler replacement, which can maximize performance while minimizing
emissions.
Cleaver-Brooks has set up an educational website at
www.cleaverbrooks.com/epa to make it easier for facility managers to understand
and comply with the EPA’s new rules for boilers. On the site, managers can find out which
rules and work practices apply to their facility, and they can download the
necessary forms for completion. For
information about fuel metering options or other compliance solutions, contact
an authorized Cleaver-Brooks representative www.cleaverbrooks.com/reps.